The house is almost fully sheathed and the garage roof is almost done!

Another 9 days gone and we are still making steady progress. Wall sheathing is starting to go up but we are still waiting on equipment to help us install the very heavy ridge beams and rafters.

The past 10 days have been very busy! We finished up the foundation and grading and made a good start on raising the timberframe.

We’re writing this post on Monday August 25 and it is the first really rainy day in a while. We’re taking a break from construction while we wait for the rain to pass.

Lots of progress!
Sunday August 10 was a day of rest! Yay! Over the next 5 days we made rapid progress toward completing the seemingly never ending projects that needed to be completed before we could actually start raising the timberframe. We are so glad to be almost done with the foundation and site prep!